Given below the cross-section details of the single-room building.
Based on the above details the following 5 building estimation quantities for the single room shall be calculated.
- Earthwork excavation quantity for the foundation
- Concrete quantity for the foundation
- CRS (crushed rouble stone) masonry quantity
- Concrete quantity in plinth beams
- 1st class brickwork in single room building superstructure.
The longwall length from centre to the centre can be calculated =6+0.5×0.230+0.5x.230=6.23 m
The short wall length from centre to the centre can be calculated =5+0.5×0.230+0.5×0.230=5.23 m.
1.Earthwork excavation quantity in foundation :
From the single-room building section, depth of foundation from ground level(GL) is 900mm (300 mm +300 mm+300 mm) and width of the foundation is 900 mm.
Total length of one long wall for foundation excavation = 6.23 m+0.45 m+0.45 m = 7.13 m
The total length of one short wall for foundation excavation =5.23 m- 0.45 m -0.45 m =4.33 m.
So, total earthwork excavation quantity in foundation for long walls = 2 nos x 7.13 m x 0.9 m depth x 0.9 m width =11.55 cum
Total earthwork excavation quantity in foundation for short walls = 2 nos x 4.33 m x 0.9m depth x 0.9 m width = 7.01 cum.
So Total building estimation item, earthwork excavation quantity for the foundation of single-room building = 11.55 cum + 7.01 cum =18.56 cum.
2.Concrete quantity for the foundation :
Total length of one long wall for foundation Concrete = 6.23 m+0.45 m +0.45 = 7.13 m
The total length of one short wall for foundation Concrete =5.23 m-0.45 m-0.45 m=4.33 m
From the single-room building section, depth of concrete foundation is 0.3 m.
So, total concrete quantity for foundation for long walls = 2 nos x 7.13 m x 0.3 m depth x 0.9 m width =3.85 cum
Total concrete quantity for foundation for short walls = 2 nos x 4.33 m x 0.3 m depth x 0.9 m width =2.33 cum
Total building estimation item, concrete quantity for foundation is 3.85 cum + 2.33 cum =6.18 cum.
3.Crushed rubble stone masonry quantity
As per the single-room building section, CRS masonry is laid in 2 steps.
In 1st step crushed rubble stone ( CRS) wall width is 600 mm and height is 300 mm.
In the 2nd step, CRS wall width is 500 mm and the depth is 300 mm.
1st step CRS wall
Long CRS wall
The total length of one long CRS wall in 1st step = 6.23 m+0.3 m + 0.3 m =6.83 m
So Total long CRS wall quantity in 1st step=2 nos x 6.83 m x 0.6 m x 0.3 m = 2.45 cum
Short CRS wall
The total length of short CRS wall in 1st step = 5.23 m – 0.3 m -0.3 m =4.63 m.
Total short CRS wall quantity in 1st step =2 nos x 4.63 m x 0.6 m x 0.3 m = 1.66 cum
2nd step CRS wall
Long CRS wall
The total length of one long CRS wall in 2nd step = 6.23 m+0.25 m + 0.25 m =6.73 m
So Total long CRS wall quantity in 2nd step=2 nos x 6.73 m x 0.5 m x 0.3 m = 2.01 cum
Short CRS wall
The total length of short CRS wall in 2nd step = 5.23 m – 0.25 m -0.25 m =4.73 m.
Total short CRS wall quantity in 2nd step =2 nos x 4.73 m x 0.5 m x 0.3 m = 1.41 cum
Total CRS masonry quantity
So Total building estimation items, CRS masonry quantity for building including 1st and 2nd step =2.45 cum +1.66 cum +2.01 cum + 1.41 cum =7.53 cum.
4.Concrete quantity in plinth beams
As per the section, the depth of the plinth beam is 600 mm and width is 400 mm.
Long plinth beam
The total length of long plinth beam = 6.23 m+0.20 m + 0.20 m =6.63 m
So Total long plinth beam concrete quantity =2 nos x 6.63 m x 0.4 m x 0.6 m = 3.18 cum
Short plinth beam
The total length of short plinth beam = 5.23 m – 0.20 m -0.20 m =4.83 m.
Total short plinth beam concrete quantity =2 nos x 4.83 m x 0.4 m x 0.6 m = 2.31 cum
Total plinth beam quantity
So Total building estimation item, plinth beam concrete quantity for building=3.18 cum +2.31 cum =5.49 cum
5.1st class brickwork in the superstructure
As per the given section, the brick wall thickness is 230 mm and height is 3.5 m.
Long brick wall
The total length of long brick wall =6.23 m+0.115 m + 0.115 m =6.46 m
So Total long wall brickwork quantity =2 nos x 6.46 m x 0.23 m width x 3.5 m height = 10.4 cum
Short brick wall
The total length of short brick wall = 5.23 m – 0.115 m -0.115m =5 m.
Total short wall brickwork quantity =2 nos x 5 m x 0.23 m x 3.5 m = 8.05 cum
Total 1st class brickwork quantity
So Total building estimation items, 1st class brickwork quantity for building=10.4 cum +8.05 cum =18.9 cum
Conclusion :
So by the above process, we can calculate 5 building estimation items of one single room.
Also Read more topics :
I don’t think the title of your article matches the content lol. Just kidding, mainly because I had some doubts after reading the article.
Can you be more specific about the content of your article? After reading it, I still have some doubts. Hope you can help me.
Thanks for posting. I really enjoyed reading it, especially because it addressed my problem. It helped me a lot and I hope it will help others too.
Thanks for excellent info I was looking for this information for my mission.
I am not sure where you’re getting your info, but good topic. I needs to spend some time learning much more or understanding more.
Thanks for wonderful information I was looking for this info for my mission.
A fascinating discussion is definitely worth comment. I think that you ought to write more on this issue, it may not be a taboo matter but typically people dont discuss these topics. To the next! All the best!!