Masonry platform building estimation, cost estimation can be done based on the provided specifications, drawings.
Masonry platform specifications, drawings
Give below the specifications:
- Masonry platform size 7 m x 6 m
- Masonry is constructed in 1st class brickwork in footings and above footings.
- Foundation is laid in cement concrete
- 25mm cement concrete flooring is laid over 75mm thick lime concrete
- Masonry walls outside are finished with 12mm thick plastering in 1:6 ratio
- For cost estimation, local rates are considered
Read More related topics :
- Retaining wall |Cost estimation 3 steps
- RCC column cost estimation in 6 steps
- Double room building estimation in 6 steps
7 steps for Masonry platform quantity estimation
The following 7 steps are involved in quantity estimation.
- Earthwork excavation quantity estimation
- Earthwork backfilling.
- cement concrete foundation.
- 1st class brickwork quantity.
- Outer walls plastering quantity.
- Cement concrete flooring quantity.
- cost estimation using local rates.
Longwall centre to centre length can be calculated by =7-(0.5×0.4)-(0.5×0.4)=6.6 m
Shortwall centre to centre length can be calculated by =6-(0.5×0.4)-(0.5×0.4)=5.6 m
1. Earthwork excavation quantity
Earthwork excavation in the foundation can be estimated by:
Length of Longwall in excavation = 6.6 m +0.8 m =7.4 m
Total longwall excavation quantity = 2 no.s x 7.4 m x 0.8 m x 0.7 m =8.28 cum
Length of short wall in excavation = 5.6 m -0.8 m =4.8 m
Total short wall excavation quantity = 2 no.s x 4.8 m x 0.8 m x 0.7 m =5.37 cum
So,total earthwork excavation in foundation=8.28 cum +5.37 cum=13.65 cum
2. Earthwork in backfilling
Above GF quantity required for backfilling can be estimated by:
Length of Longwall for backfilling = 6.6 m -0.4 m =6.2 m
Length of the short wall for backfilling = 5.6 m -0.4 m =5.2 m
Height of the platform required for backfilling= 2 m-0.075 m =1.925 m
where= 0.075 m is flooring thickness,2 m is the total height of the platform.
So,total earthwork quantity required for backfilling=6.2 m x 5.2 m x 1.925 m =62.06 cum
3. Cement concrete in foundation quantity
Cement concrete in the foundation can be estimated by:
Length of Longwall in foundation = 6.6 m +0.8 m =7.4 m
Total longwall cement concrete quantity = 2 no.s x 7.4 m x 0.8 m x 0.2 m =2.36 cum
Length of short wall in foundation = 5.6 m -0.8 m =4.8 m
Total short wall cement concrete quantity = 2 no.s x 4.8 m x 0.8 m x 0.2 m =1.53 cum
So,total cement concrete in foundation=2.36 cum +1.53 cum=3.89 cum
4. 1st class brickwork quantity
1st class brickwork quantity in footings and above footings can be calculated by:
In 1st footings
Length of Longwall in 1st footing = 6.6 m +0.6 m =7.2 m
Total longwall brickwork quantity in 1st footing = 2 no.s x 7.2 m x 0.6 m x 0.2 m =1.72 cum
Length of short wall in 1st footing = 5.6 m -0.6 m =5 m
Total short wall brickwork quantity in 1st footing = 2 no.s x 4.8 m x 0.6 m x 0.2 m =1.15 cum
So,total brickwork quantity in 1st footing=1.72 cum +1.15 cum=2.87 cum
In 2nd footings
Length of Longwall in 2nd footing = 6.6 m +0.5 m =7.1 m
Total longwall brickwork quantity in 1st footing = 2 no.s x 7.1 m x 0.5 m x 0.1 m =0.71 cum
Length of short wall in 2nd footing = 5.6 m -0.5 m =5.1 m
Total short wall brickwork quantity in 2nd footing = 2 no.s x 5.1 m x 0.5 m x 0.1 m =0.51 cum
So,total brickwork quantity in 2nd footing=0.71 cum +0.51 cum=1.22 cum
Above footing
Length of Longwall in above footing = 6.6 m +0.2 m +0.2 m=7.0 m
Height of the wall from above footing to top =2 m +0.2 m = 2.2 m
Total longwall brickwork quantity in above footing = 2 no.s x 7.0 m x 0.4 m x 2.2 m =12.32 cum
Length of short wall above footing = 5.6 m -0.2 m-0.2 m =5.2 m
Total short wall brickwork quantity in above footing = 2 no.s x 5.2 m x 0.4 m x 2.2 m =9.15 cum
So total brickwork quantity in above footing =12.32 cum + 9.15 cum =21.47 cum
So total 1st class brickwork quantity in footings and above footings = 2.87 cum+1.22 cum+21.47 cum=25.56 cum
5. Outside walls 12mm thick plastering quantity
Length of Longwall for plastering = 6.6 m +0.2 m +0.2 m=7.0 m
Height of the wall from above footing to top =2 m +0.2 m = 2.2 m(including 20mm below GL)
Total longwall plastering quantity = 2 no.s x 7.0 m x 2.2 m =30.8 sq.m
Length of short wall for plastering = 5.6 m +0.2 m+0.2 m =6 m
Total short wall plastering quantity = 2 no.s x 6 m x 2.2 m =26.4 sq.m
So total 12 mm thick plastering quantity =30.8 sq.m + 26.4 sq.m =57.2 sq.m
6. Cement concrete flooring quantity
cement concrete on compacted soil
100 mm thick cement concrete 1:2:4 is laid on the compacted soil.
Length of the longwall = 6.6-0.2-0.2=6.2 m.
Length of short wall = 5.6-0.2-0.2=5.2
Cement Concrete quantity on floor = 6.2 x 5.2 x0.1 = 3.22 cum.
Cement concrete on brick wall
25 mm thick cement concrete 1:2:4 is laid on brickwork
Length of long brickwall = 6.6 + 0.2+0.2=7 m
Cement concrete on long brickwall = 2 nos x7 m x0.4 mx 0.025 m=0.14 cum
length of short brick wall = 5.6-0.2-0.2=5.2 m
Concrete quantity on short brick wall =2 nos x5.2 m x0.4 m x0.025 m=0.104 cum
So total cement concrete quantity in 1:2:4 ratio = 3.22 cum +0.14 cum +0.104 cum=3.46 cum
Cost estimation
For cost estimation all rates includes with labour and materials
S.No | Work Description | Estimated Quantity | Unit | Rate | Amount |
1 | In foundation Earthwork excavation | 13.65 | cum | 350 | 4777.50 |
2 | Earth work in back-filling | 62.06 | cum | 250 | 15515 |
3 | Cement concrete in foundation | 3.89 | cum | 3600 | 14004 |
3 | 1st class brickwork | 25.56 | cum | 4600 | 117576 |
4 | Outside walls 12 mm thick plastering | 57.2 | Sq.m | 310 | 17732 |
5 | 1:2:4 cement concrete | 3.46 | cum | 3600 | 12456 |
Total in Rs | 182060.50 | ||||
Add 5% contingency to total cost estimation | 191163.53 |
So,total cost estimation of masonry platform is Rs 191163.53 including all manpower and materials.
Conclusion:
From the above 7 steps cost estimation of masonry platform as be calculated easily.
Also Read related topics:
Thank you, I have recently been looking for information about this topic for a long time and yours is the best I’ve found out so far. However, what concerning the conclusion? Are you sure in regards to the supply?
Your point of view caught my eye and was very interesting. Thanks. I have a question for you.
Great content! Super high-quality! Keep it up!
Thank you for sharing this article with me. It helped me a lot and I love it.
Excellent read, I just passed this onto a friend who was doing a little research on that. And he actually bought me lunch as I found it for him smile Thus let me rephrase that: Thank you for lunch!
I don抰 even understand how I stopped up here, but I believed this publish used to be great. I do not recognize who you might be however certainly you are going to a famous blogger if you happen to aren’t already 😉 Cheers!
An attention-grabbing discussion is worth comment. I think that you should write extra on this topic, it might not be a taboo subject however typically persons are not enough to speak on such topics. To the next. Cheers
Sure.Thank you