RCC column cost estimation in 6 steps

rcc column plan

RCC Column cast in the foundation footing cost estimation can be estimated from the provided plan, section drawings, local work rates.

RCC Column specification, plan and section details

rcc column plan
RCC column plan
  • Footing size is 2 m length x 2 m wide x 0.45 m depth
  • PCC 1:4:8 is utilised in foundation
  • RCC 1:2:4 is utilised in footing
  • 300 dia is the column size above plinth level,350 mm x 350 mm is the size from footing top-level to plinth level and  the RCC 1:2:4 is utilised,
  • Reinforcement 12 mm dia @150 mm c/c both sides is utilised in footing
  • Main bars 6 numbers 16 mm dia and stirrups 10mm dia @ 150 mm c/c is utilised in the column.
rcc column section
rcc column section

RCC column quantity, cost estimation

The following 6 steps are involved in the estimation

  1. In foundation earthwork excavated quantity estimation.
  2. PCC quantity estimation in foundation quantity.
  3. RCC quantity estimation in the footing
  4. RCC quantity estimation in column
  5. Reinforcement quantity estimation in footing and column
  6. Total cost estimation of all works

1. In foundation earthwork excavated quantity estimation

From the above-mentioned section depth of foundation excavated=0.83m.From specifications and plan length of foundation is 2 m and width is 2 m.

Earthwork excavated quantity can be estimated by=2 m length x2 m wide x 0.83 m depth=3.32 cum.

2. PCC quantity estimation in foundation quantity.

From the section, the depth of PCC in the foundation is 80 mm. From the plan length of the foundation is 2 m and the width is 2 m.

Plain cement concrete, PCC  1:4:8 is utilised in the foundation.

PCC quantity can be estimated by=2 m length x 2 m width  x 0.08 m depth=0.32 cum.

3. RCC quantity estimation in the footing

RCC 1:2:4 is utilised in footing.

From the section length of footing is 2 m, width of footing is 2 m and depth is 0.45 m

RCC quantity in footing can be calculated by = 2 m x 2 m x 0.45 m =1.8 cum.

Single room |5 building estimation items

4. RCC quantity estimation in column

RCC 1:2:4 is utilised. From the specifications,300 dia is the size and 3.3 m is the height from plinth level to slab bottom,350 mm x 350 mm is the size and height 900 mm from footing top-level to plinth level.

Quantity from footing top-level to plinth level

Concrete quantity from footing top-level to plinth level can be calculated by =0.35 m x 0.35 m x 0.9 m=0.11 cum

Quantity from footing plinth level to slab bottom

Concrete quantity from plinth top-level to slab bottom level can be calculated by =3.14 x (0.3 m x 0.3 m )/4x 3.3 m=0.233 cum

So, the total concrete quantity  =0.11 cum + 0.233 cum=0.343 cum

5. Reinforcement quantity estimation in footing and column

From specifications, Reinforcement 12 mm dia @150 mm c/c both sides is utilised in footing.

Main bars 6 numbers 16 mm dia and stirrups 10mm dia @ 150 mm c/c is utilised

Reinforcement quantity in footing

Length of the footing is 2 m and width is 2 m, clear cover =40mm

No. of bars =(clear length/spacing) +1

Clear length=total length-2 x clear cover=2 m-2 x 0.04m=1.92 m

Total No.of bars along the length of footing=(1.92/0.15)+1= 14 bars.

Similarly, Total No.of bars along the width of footing=(1.92/0.15)+1= 14 bars.

The total length of steel bar=length-2x clear cover +20 x dia.steel=2 m -2 x 0.04+ 20×0.012=2.16 m.

Unit Weight of steel= (steel dia x steel dia) /162= 12 x 12/162=0.89 kg/m

Total weight of steel quantity in footing can be calculated by=2 ways x No’s of bars x total steel length x unit weight of steel

=2 x 14 no’s x 2.16 m x 0.89 kg/m =53.82 kgs

Reinforcement quantity in column from footing to slab bottom

Length is 300 mm dia, clear cover =40mm

Main bars weight

No. of main bars =6 no’s

Total length of bar from footing to slab bottom =0.45 m+0.3 m +bottom bent-clear cover+0.6 m+3.3 m+top bent=0.45+0.3+0.15-0.08+0.6+3.3+0.1=4.89 m

Unit weight =dia x dia/162=16 x 16/162=1.58 kg/m

Total weight of main bars =No.of bars x total length x unit weight=6No’s x 4.89 m x 1.58 kg/m=46.35 kgs

Stirrups weight

For stirrups 10mm dia @ 150 mm c/c is utilised.

Length in which stirrups is utilised =3.3 m +0.6 m +0.3 m=4.2m

No. of bars =(clear length/spacing) +1

So, No of bars=(4.2/0.15)+1=29 no’s

Clear length of bar=3.14 x (total dia-2 x clear cover)=3.14 x (0.3 m-2 x 0.04m)=0.7 m

Unit Weight of steel= (steel dia x steel dia) /162= 10 x 10/162=0.62 kg/m

Total weight of steel quantity in stirrups can be calculated by= No’s of bars x total steel length x unit weight of steel

= 29 no’s x 0.7 m x 0.62 kg/m =12.58 kgs

So,total weight of steel in footing and column=53.82 kgs +46.35 kg +12.58 kg=112.75 kg=0.112 MT

6. Total cost estimation of all works

For total cost estimation,local rates which includes material and labour are considered for all works.

Rate of cement concrete includes material and labour cost of shuttering but excludes steel material and labour cost are considered in the cost estimation.

Rate of steel includes material and labour charges are considered in cost estimation.

S.NoDescription of workQuantityRateAmount
1In foundation excavated earth3.32 cumRs.350Rs.1162
2PCC in foundation0.32 cumRs.3200Rs.1024
3Cement concrete in footing1.8 cumRs.3800Rs.6840
4Cement concrete in column0.343 cumRs.4400Rs.1509.2
5Reinforcement in footing and columns0.112 MTRs.10200Rs.1142.4
TotalRs.11677.6
5% contigency is addedRs.12261.48
Total cost estimation of all works

Conclusion:

RCC column
RCC column

So from the above steps cost estimation can be calculated very easily.

Read Also:

Double room building estimation|6 steps

Masonry platform cost estimation:7 steps

About Ashwini Kumar

Ashwini Kumar is a graduate in civil engineering from NIT Warangal. He has 8+ years of experience in the construction field. He is the author, founder of the Easy Home Builds blog

View all posts by Ashwini Kumar →

17 Comments on “RCC column cost estimation in 6 steps”

  1. You actually make it seem so easy with your presentation but I to find this topic to be actually something which I think I would never understand. It kind of feels too complex and extremely wide for me. I’m looking forward on your next post, I will try to get the hang of it!

  2. There are some attention-grabbing time limits on this article however I don抰 know if I see all of them middle to heart. There may be some validity however I’ll take maintain opinion until I look into it further. Good article , thanks and we would like extra! Added to FeedBurner as properly

  3. You actually make it seem so easy along with your presentation but I find this matter to be actually something which I think I’d by no means understand. It sort of feels too complex and very extensive for me. I am taking a look forward on your next put up, I抣l try to get the dangle of it!

  4. Greetings I am so excited I found your blog page, I really found you by error, while I was searching on Yahoo for something else, Nonetheless I am here now and would just like to say thanks a lot for a tremendous post and a all round thrilling blog (I also love the theme/design), I don抰 have time to browse it all at the minute but I have bookmarked it and also included your RSS feeds, so when I have time I will be back to read much more, Please do keep up the awesome job.

  5. We are a group of volunteers and opening a brand new scheme in our community. Your site provided us with useful information to paintings on. You’ve performed an impressive job and our entire community shall be thankful to you.

  6. Good day! This is kind of off topic but I need some advice from an established blog. Is it difficult to set up your own blog? I’m not very techincal but I can figure things out pretty fast. I’m thinking about creating my own but I’m not sure where to start. Do you have any ideas or suggestions? Cheers

  7. I do not even know how I ended up here, but I thought this post was good. I do not know who you are but definitely you’re going to a famous blogger if you aren’t already 😉 Cheers!

  8. Spot on with this write-up, I actually suppose this website needs much more consideration. I抣l in all probability be again to learn rather more, thanks for that info.

  9. Wow! This could be one particular of the most beneficial blogs We’ve ever arrive across on this subject. Actually Wonderful. I’m also an expert in this topic so I can understand your hard work.

Leave a Reply to Hairstyles Cancel reply

Your email address will not be published. Required fields are marked *