Critical path method|12 technical terms

Critical path method is the technique of network to deal with large and complex projects.

It is a project management technique.

What is the Critical path method [C.P.M] in project management?

critical path method
critical path method-Network diagram
This critical path  method was developed in 1957 and
it is suitable for both civil and mechanical engineering projects.
This technique is useful to determine how best to reduce the time required to perform production, maintenance and construction and also to minimize the direct and indirect cost of the project.
Using this critical path method C.P.M, a planning engineer will come to know the sequence of the various activities of the project.
Critical path network can be prepared using the below steps :
  1. Preparation of network
  2. Estimation of the expected time to perform each activity.
  3. Determination of critical path schedule.
  4. Interpretation of the results.

Important 12 technical terms used in critical path method ,C.P.M

The following are the 12 technical terms used in critical path method
  1. Activity
  2. Dummy activity
  3. Event
  4. Network
  5. Early start time (E.S.T)
  6. Early finish time (E.F.T)
  7. Late start time
  8. Late finish time
  9. Total float
  10. Free float
  11. Critical activities
  12. Critical path

1. Activity

Activity is part of the project. The network of the project is denoted by an arrow.
The start of the activity is indicated by the tail of the arrow and
the end of the activity is indicated by the head of the arrow.
For a given duration of an activity only one arrow is utilised.
The arrows on the activity are not represented to scale.
Along with the arrows, the duration of the activity is shown
For example:
Between 2 and 4 arrows activity C is shown ,and its 4 units of time duration is shown beneath the arrow.

2.Dummy activity

The dummy activity is the activity which does not ustilise any time or any resources for the completion of activity .

3.Event

An event is the stage or point at which all previous completed activities merge and
jobs coming out of this point needs to be finished.
At the junctions of arrows, they are represented by circles or nodes.
In sequential order, they are serially numbered.

4. Network

The representation of the entire project  activities in diagrammatically is termed as network.
On this diagram, The various projects jobs  which are expected to be completed are shown in the order.

5. Early start time

An early start is the earliest possible time at which an activity may start.

6.Early finish time

Early finish time is the sum of the earliest start time of activity and the time required for its completion.

7.Late start time

Without delaying the project date, the most possible time at which an activity may start is termed as late start time.

8.Late finish time

The sum of the time required for completion and the  late start time of activity is termed as late finish time.

9. Total float

The difference between the estimated  duration and maximum allowed time for an activity is termed as total float.
Without disturbing the project schedule it is the span of time by which the activity can start.
It is expressed  by letter S.

10. Free float

The span of time  without disturbing  the start of succeeding activities by which the activity completion can be delayed is termed as Free float.
It is expressed by S.F.

11.Critical activities

The events which have no float are termed as critical activities.
All the critical activities need to be finished  on schedule.

12.Critical path

Thejoining of the critical events in the network path is termed as critical path .

Basic rules for critical path method network:

The following are the main rules of Critical path method network.
  1. The flow direction is indicated by arrows, which is normally accepted from left to right.
  2. The length duration of the activity is not correspond to length of the arrow.  It is just  geometrical configuration and does not have any importance.
  3. The activities merging at it must be completed before starting any new activity.
  4. The indication of the logical conditions of dependency in a network is done by an arrow.
  5. The construction of network is done logically on the principle of dependency.
  6. For starting the project and also for closing the project  only one event must be there in every  network.
  7. These connection of any two events may be done directly but not with more than one activity.
  8. Serial numbers should be given to events and those numbers should not done duplication in a network.

Drawing a Network in critical path method

The following information is needed for drawing a network of any project.
  1. List all the activities required for completion of a project.
  2. Ascertain the dependence of the activities on each other.
  3. Draw a network of the activities roughly with a soft pencil so that it can be easily erased.
  4. The duration of each activity can be estimated by keeping in mind about the availability of equipment, manpower and also the likelihood of activities delays.
  5. The estimate time of each activity needs to be noted.
  6. For deciding the critical path,the latest and earliest allowable start and finish times for every activity to determined.
  7. In the field need to finalise the network for use.

Advantages of critical path method

The important advantages of critical path method are:
  1. It is useful to ascertain the time schedule
  2. It helps to have proper control of the project.
  3. It enables better and detailed planning.
  4. It is very helpful to communicate the cost, project schedule, project planning ,performance ,time and project planning.
  5. The critical activities which are highlighted along the critical path should  be attended with care until their completion.
Despite the great planning cost of a project, Critical path proves to be very useful for focussing the attention of project engineers on the critical path activities and thus avoids unnecessary expenditure.

Expected length of the project , the critical path

1. Critical path :

The longest duration path of a network.
 The sum of the expected times of the total activities is maximum in this path.

2. Length of the project

The sum of the expected times of all the activities along the critical path of the network of a project is called the length of the project.

3. The variance of the project

The variance of the project is the total sum of the variance along the critical path  the activities of the network of a project.

4. The standard deviation of the project

The standard deviation is the square root of the variance which is calculated along the network  critical path of a project.

Technical terms used in critical path method

  1. Independent float
  2. Total float
  3. Milestone
  4. Cost slope

1. Independent float

The free slack or independent float is the  difference between the  the minimum total float of all its immediate successors  and the activities total float.

2. Total float

The total floats is the  difference between the early and late finish times of an activity.
There will be zero total floats for the critical path activities.

3.Milestone

An even or the mile stone is the point in time which represents the beginning of the completion of the same activity or group of activities on the project network.

4.Cost slope

The relationship between  the trade-off and time-cost for an individual activity is assumed linear and expressed by a straight line on a graph plotting activity duration versus cost.
The straight line slope  is called cost slope.
The greater is the cost of expediting the activity,the steeper the slope of this cot line.
As the duration reduced cost goes up which is indicated by the straight line which slopes down to right.
The line will be critical, If an activity time can’t be reduced even after extra resources applies to it.
Read more:

About Ashwini Kumar

Ashwini Kumar is a graduate in civil engineering from NIT Warangal. He has 8+ years of experience in the construction field. He is the author, founder of the Easy Home Builds blog

View all posts by Ashwini Kumar →

25 Comments on “Critical path method|12 technical terms”

  1. I have witnessed that intelligent real estate agents all around you are starting to warm up to FSBO Advertising and marketing. They are realizing that it’s in addition to placing a sign post in the front yard. It’s really about building relationships with these traders who at some point will become consumers. So, if you give your time and energy to encouraging these retailers go it alone : the “Law of Reciprocity” kicks in. Great blog post.

  2. You really make it seem so easy with your presentation but I find this topic to be actually something which I think I would never understand. It seems too complicated and very broad for me. I am looking forward for your next post, I抣l try to get the hang of it!

  3. Great post. I used to be checking continuously this blog and I’m inspired! Very helpful information particularly the closing part 🙂 I deal with such info a lot. I was seeking this certain information for a long time. Thank you and best of luck.

  4. I do consider all of the concepts you have introduced in your post. They’re very convincing and can certainly work. Nonetheless, the posts are too quick for newbies. May just you please extend them a little from next time? Thank you for the post.

  5. Its like you read my mind! You seem to know a lot about this, like you wrote the book in it or something. I think that you could do with some pics to drive the message home a little bit, but other than that, this is wonderful blog. An excellent read. I will definitely be back.

  6. Hey! Would you mind if I share your blog with my zynga group? There’s a lot of folks that I think would really appreciate your content. Please let me know. Thanks

  7. I抦 impressed, I have to say. Really hardly ever do I encounter a blog that抯 each educative and entertaining, and let me let you know, you have got hit the nail on the head. Your thought is outstanding; the problem is something that not enough individuals are speaking intelligently about. I’m very glad that I stumbled throughout this in my search for one thing relating to this.

  8. Great beat ! I would like to apprentice while you amend your web site, how could i subscribe for a blog site? The account helped me a acceptable deal. I had been a little bit acquainted of this your broadcast provided bright clear concept

  9. Hi there, simply became aware of your blog via Google, and found that it is really informative. I am going to watch out for brussels. I?ll appreciate in the event you proceed this in future. Numerous people will be benefited from your writing. Cheers!

Leave a Reply to Beauty Fashion Cancel reply

Your email address will not be published. Required fields are marked *